Size a grounding electrode conductor from Table 250.66, an equipment grounding conductor from Table 250.122 (including the 250.122(B) proportional increase), and a supply-side or main bonding jumper from Table 250.102(C)(1) — the same table values as 250.66, including the 12½% note for large conductors. These tables are the same in the 2020 and 2023 editions. The field guide below covers ground rods (250.53), concrete-encased electrodes (Ufer), and intersystem bonding (250.94).

1 · Grounding electrode conductor (250.66)

250.66 sizes the GEC from the largest ungrounded service-entrance conductor or the equivalent area of parallel conductors. The GEC to a rod, pipe, or plate electrode need not be larger than 6 AWG copper (or 4 AWG aluminum) (250.66(A)). The GEC to a concrete-encased electrode need not be larger than 4 AWG copper (250.66(B)). The GEC to a ground ring need not be larger than the ring conductor (250.66(C)). Protect the GEC from physical damage (250.64); where PVC is used for protection, 2020+ requires Schedule 80 (250.64(B)).

2 · Equipment grounding conductor (250.122)

If you increased the ungrounded conductors from the minimum size that has sufficient ampacity for the load (for voltage drop or any other reason), 250.122(B) requires the EGC to be increased in proportion to circular mils. The EGC is not required to be larger than the ungrounded conductors (250.122(A)).

3 · Supply-side / main bonding jumper (250.102 / 250.28)

The supply-side bonding jumper and the main bonding jumper use Table 250.102(C)(1) — enter the ungrounded conductors in section 1. The result is shown here as well. Load-side equipment bonding jumpers are sized from Table 250.122 (section 2) based on the OCPD ahead of the circuit.

4 · Ground rods — 250.53

5 · Concrete-encased electrode (Ufer) — 250.52(A)(3)

6 · Intersystem bonding — 250.94

Reference only — not engineering, legal, or code-compliance advice. Results are estimates for qualified persons and must be verified against the NEC edition adopted where the work is done (your selected edition), manufacturer instructions, and the local AHJ. Use is subject to the Terms of Use & Disclaimer. — Morningstar Electric LLC