Offline mode — all calculators still work · Morningstar Electric LLC
Morningstar Electric LLC ★
How to Test a Capacitor
⌂ Home

How to Test a Run / Start Capacitor

General field practice for qualified electricians. The equipment manufacturer's instructions, your adopted code edition, and the AHJ govern where they differ.

⚠ Capacitors hold a charge after power is off. Turn off and lock out the disconnect, verify zero voltage, then discharge the capacitor across its terminals (each section of a dual cap) with an insulated discharge tool or a resistor (for example about 20 kΩ, 5 W) before you touch the terminals. Don't short the terminals with a screwdriver.

1 · Identify the capacitor

2 · Visual check

3 · Meter test (power off)

  1. Lock out, verify, and discharge (see the warning above). Photograph or label the wires, then remove them.
  2. Set the meter to capacitance (µF). Measure C–HERM and C–FAN on a dual cap, or across the two terminals of a single cap.
  3. Compare to the label using the tolerance. Use the checker below.
  4. Also check each terminal to the metal can. It should read open. Any continuity to the case means the capacitor has failed.

4 · Under-load test (running)

Use this when you can't remove the capacitor, or to confirm it under operating conditions. Work live only with the PPE and procedures your arc-flash and shock risk assessment requires.

  1. With the unit running, clamp the wire from the capacitor's HERM (or FAN) terminal. That is the start-winding current through the capacitor, in amps.
  2. Measure voltage across the same capacitor terminals (C to HERM, or C to FAN). It is usually higher than line voltage because of the motor's back EMF.
  3. Calculate: µF = 2652 × A ÷ V at 60 Hz (or 3183 × A ÷ V at 50 Hz). The constant comes from C = I ÷ (2πfV) × 10⁶.

5 · Capacitor calculator

6 · What the result means

Reference only — not engineering, legal, or code-compliance advice. Results are estimates for qualified persons and must be verified against the NEC edition adopted where the work is done (your selected edition), manufacturer instructions, and the local AHJ. Use is subject to the Terms of Use & Disclaimer. — Morningstar Electric LLC